Multi-criteria analysis of the runway options and evidence to the hearings panel for a nationally significant infrastructure approval.

2019approval granted
Optionstested for length and location

The question

Auckland Airport needed approval for a second runway, with several options for its length and location, and strong opposition to address. The airport wanted the best option, and evidence that would hold up.

What we did

We ran a multi-criteria analysis of the options, tested how sensitive the ranking was to different scores and weights, and wrote it up in plain English. The report later formed the basis of evidence to the hearings panel.

The result

Planning approval for the runway was granted in 2019. The airport's 2026 master plan retains the second runway as a staged option, with no construction date set.